Civil Infrastructure Works for the week commencing 11 November 2019

  • Completed section of Footpath at Bundarra (see photo)
  • Complete preparation for earth works on Noalimba Avenue
  • Continue grading Lindon Road
  • Continued footpath in Maitland Street
  • Continue tar patching on rural Roads
  • Heavy patching works on Bundarra Road (MR124)

 

Myall-Creek-Box-Culverts.jpg

 

Works scheduled next week, commencing 18 November 2019:

  • Continue tar patching on rural roads
  • Continue formwork for Myall Swamp box culvert
  • Continue grading Lindon Road
  • Continue shared footpath in Maitland St between John St and East St
  • Continue reading water meters
  • Continue carting sub base gravel for Noalimba avenue construction and install new pipes for better drainage 
  • Commence extension of pipes on Bingara Rd next construction job
  • Heavy patching works on Bundarra Road (MR124)
  • Continue tree watering in Alma Park