Council Works Report 10 June 2022

Civil Infrastructure Works for the week ending 10 June 2022

  • Continued drainage ready for boxing out shoulders on Hawthorne Drive
  • Continued grading Hillview Road
  • Completed grading Old Kingstown Road
  • Completed patch grading on Barraba Road
  • Commenced school crossings Wood Street (see photo)
  • Continued tar patching on rural and regional roads
  • Completed mowing Bundarra
  • Completed water meter reading Uralla and Bundarra
  • Continued maintenance kerb blisters
  • Continued Fuller Park Upgrade
  • Continued sign maintenance on rural roads and in Uralla
  • Completed Bowline Street school crossing (except fencing awaiting materials)
  • Completed patch graveling Mount Butler Road at Kalinda Road intersection
  • Completed dig out on Baldersleigh Road

School-Crossing-at-Wood-Street.jpg

 

Works scheduled next week, commencing 14 June 2022

  • Continue drainage and start graveling shoulders on Hawthorne Drive Construction (see photo)
  • Continue grading Hillview Road
  • Commence grading Mount Drummond Road
  • Continue tar patching rural and regional roads
  • Continue mowing in Uralla and Bundarra
  • Continue drainage in Uralla and rural roads
  • Continue maintenance kerb and gutters
  • Complete Fuller Park upgrades (awnings and tables)
  • Complete Wood Street school crossing Uralla
  • Commence Park Street school crossing Uralla