Council Works Report 3 September 2021

Civil Infrastructure Works for the week ending 3 September 2021

  • Completed grading Baldersleigh Road
  • Completed grading Bindawalla Road
  • Completed grading Colomendy Road
  • Commenced grading Johnsons Road
  • Continued tar patching on regional roads (see photo)
  • Continued street furniture refurbishment
  • Continued sign maintenance in Uralla and rural roads
  • Continued with Tolleys Gully Bridge abutments (see photo)
  • Continued Hawthorne Drive construction
  • Continued preparing and forming up Old Gostwyck, Corey & Hariet Gully Roads for sealing
  • Completed grading Glenburnie Road
  • Completed grading Waterworks Road
  • Commenced grading Green Gully Road
  • Continued Bendemeer Street Bundarra footpath upgrade (see photo)
  • Sprayed sports fields and cemetery for broadleaf and bindii
  • Raised the tree canopy clearance in Alma Park

Works scheduled next week, commencing 6 September 2021

  • Continue tar patching on rural and regional roadsRural-Road-Maintenence.jpg
  • Continue drainage maintenance in Uralla and rural roads
  • Continue street furniture refurbishment
  • Continue multipurpose sports courts landscaping in Bundarra
  • Continue Tolleys Gully Bridge abutments
  • Continue Hawthorne Drive Construction Stage 1
  • Continue preparing and forming up Old Gostwyck, Corey & Hariet Gully Roads for sealing
  • Continue Bendemeer Street footpath upgrade in Bundarra
  • Continue grading Johnsons Road
  • Commence grading Invergowrie area
  • Commence grading Mihi/Enmore area