Council Works Report 9 September 2022

Civil Infrastructure Works for the week ending 9 September 2022

  • Complete grading Lawson Road
  • Complete grading Yellowbox Drive
  • Complete grading Mundays Lane
  • Complete spot graveling on Panseyfield and Primrose Roads
  • Ceased grading Devoncourt Road until it dries out
  • Commence grading Athol Road
  • Complete grading Georges Creek Road
  • Complete grading Clerks Creek Road
  • Continue tar patching rural roads
  • Continue tar patching regional roads
  • Continue street furniture refurbishing in main street
  • Continue mowing in Uralla and Bundarra
  • Continue weed spraying in Uralla and Bundarra
  • Commence tree pruning in Uralla and Bundarra

 

Works scheduled next week, commencing 12 September 2022

  • Complete grading Panseyfield Road
  • Complete grading Primrose Road
  • Continue grading Athol Road
  • Commence grading Baldersleigh Road
  • Commence gravel patch Northeys Road ready for stabilising
  • Commence heavy patch on Kingstown Road
  • Commence heavy patch on Warrabah Road
  • Commence drainage on Bindawalla Road
  • Continue Roman Street kerb and guttering
  • Continue tar patching on rural and regional roads
  • Continue tree pruning in Uralla and Bundarra
  • Continue mowing in Uralla and Bundarra
  • Continue street furniture refurbishing in main street

 