Council Works Report 14 April 2023

Civil Infrastructure works undertaken week ending 21 April 2023:

  • Continue drainage from Lone Pine Bridge to the Sporting Club on Mr73 North
  • Complete grading shoulders on sealed section of Gostwyck Road
  • Commence setting out and drainage on Gostwyck Road rehabilitation
  • Complete pouring causeway on Dog Trap Road ready to open Monday
  • Complete grading Looanga Road
  • Complete grading Balala Road
  • Complete grading Larna Road
  • Complete tar patching Mr73 South (Walcha)
  • Complete patching Flat Rock Road
  • Commence grading Dog Trap Road
  • Complete weeding and mowing in Alma Park ready for Anzac Day
  • Complete trimming trees in Hill Street
  • Continue gutter maintenance in Uralla
  • Continue mowing and weed spraying in Uralla and Bundarra

 

Planned works for week commencing 24 April 2023:

  • Complete drainage from Lone Pine Bridge to the Sporting Club Mr73 North ready for sealing
  • Commence graveling Gostwyck Road Rehabilitation
  • Complete grading Dog Trap Road
  • Commence grading Retreat Road
  • Continue tar patching on rural and regional roads
  • Continue mowing and weed spraying in Uralla and Bundarra
  • Commence marking lines for small schools athletic carnival and cross country
  • Commence renewing pipes on rural roads
  • Complete opening causeway on Dog Trap Road
  • Complete cleaning up after the Anzac Day

 

 

 

 

 

 