Council Works Report 14 April 2023
Civil Infrastructure works undertaken week ending 21 April 2023:
- Continue drainage from Lone Pine Bridge to the Sporting Club on Mr73 North
- Complete grading shoulders on sealed section of Gostwyck Road
- Commence setting out and drainage on Gostwyck Road rehabilitation
- Complete pouring causeway on Dog Trap Road ready to open Monday
- Complete grading Looanga Road
- Complete grading Balala Road
- Complete grading Larna Road
- Complete tar patching Mr73 South (Walcha)
- Complete patching Flat Rock Road
- Commence grading Dog Trap Road
- Complete weeding and mowing in Alma Park ready for Anzac Day
- Complete trimming trees in Hill Street
- Continue gutter maintenance in Uralla
- Continue mowing and weed spraying in Uralla and Bundarra
Planned works for week commencing 24 April 2023:
- Complete drainage from Lone Pine Bridge to the Sporting Club Mr73 North ready for sealing
- Commence graveling Gostwyck Road Rehabilitation
- Complete grading Dog Trap Road
- Commence grading Retreat Road
- Continue tar patching on rural and regional roads
- Continue mowing and weed spraying in Uralla and Bundarra
- Commence marking lines for small schools athletic carnival and cross country
- Commence renewing pipes on rural roads
- Complete opening causeway on Dog Trap Road
- Complete cleaning up after the Anzac Day