Civil Infrastructure works undertaken week ending 17 May 2024:
- Seal final section Tolleys/Scrubby rehabilitation
- Guidepost and spot mark Tolleys/Scrubby
- Pipe and drainage works Tolleys/Scrubby
- Complete grading Hillview Road
- Commence grading Balala Road
- Continue grading Old Kingstown Road
- Assist with water main replacement in Hill Street
- Complete water meter reading
- Continue tar patching regional roads
- Depot preliminary works for asbestos removal
- Continue maintenance footpaths, parks and cemeteries
Planned works for week commencing 20 May 2024
- Install and replace new guardrail at Tolley/Scrubby and Two Mile
- Commence preliminary works for Wallaby Rocks (Kingstown Road) rehabilitation
- Continue grading Balala Road
- Continue grading Old Kingstown Road
- Complete pipe and drainage works Tolleys/Scrubby
- Continue tar patching regional roads
- Continue Depot preliminary works for asbestos removal
- Complete final sculpture works – The Glen
- Continue maintenance footpaths, parks and cemeteries