Council Works Report 30 September 2022

Civil Infrastructure Works for the week ending 30 September 2022

  • Commence stabilising Hawthorne Drive construction
  • Complete heavy patch Terrible Vale Road
  • Complete heavy patch Kingstown Road
  • Complete gravel patch Yarrowyck Crossing Road
  • Complete gravel patch flood damage Old Wollun Road
  • Complete gravel patch flood damage Bundarra area rural unsealed roads
  • Complete gravel patch Uralla area rural unsealed roads
  • Complete drainage works East Street using contractor
  • Commence flood damage repairs Blue Mountain Road using contractor
  • Cease work on Roman Street kerb and guttering due to wet weather
  • Continue tar patching MR73 Bundarra Road
  • Continue mowing in Uralla and Bundarra
  • Continue weed spraying in Uralla and Bundarra

 

Works scheduled next week, commencing 4 October 2022

  • Complete stabilising Hawthorne Drive construction
  • Commence stabilising Northeys Road
  • Commence installing new culverts and graveling Bindawalla Road
  • Complete grading Athol Road
  • Commence grading Kingstown Bendemeer Road
  • Commence heavy patch Mount Drummond Road
  • Continue tar patching MR73 Bundarra Road
  • Complete flood damage repair Blue Mountain Road using contractor
  • Commence drainage and flood damage repairs Hillview Road using contractor
  • Continue mowing in Uralla and Bundarra
  • Continue weed spraying in Uralla and Bundarra

 

Rural-Road-Maintenence.jpg