Council Works Report 31 March 2023
Civil Infrastructure works undertaken week ending 31 March 2023:
- Complete sealing and guide posting Hawthorne Drive Construction (weather pending)
- Continue drainage in Bundarra
- Continue drainage from Lone Pine Bridge to the Sporting Club in Bundarra
- Complete grading Allinghams Road
- Complete grading Balala Road to Larna Road
- Commence grading Danehurst Road
- Continue grading Gostwyck Road shoulders
- Commence renewing causeway on Dog Trap Road
- Complete pouring slab and putting guard rail up at the Uralla Landfill shed
- Complete tar patching on Mr124 Bundarra Road
- Continue tar patching on rural roads
- Continue drainage in Uralla and rural roads
- Continue sign maintenance on rural roads
- Continue mowing and weed spraying in Uralla and Bundarra
- Complete mowing recreation areas out of town
- Continue cleaning kerb and gutters in Uralla
Planned works for week commencing 3 April 2023:
- Complete drainage in Bundarra
- Continue drainage from Lone Pine Bridge to the Sporting Club in Bundarra
- Complete grading shoulder on Gostwyck Road
- Commence boxing out Gostwyck Road construction
- Continue grading Danehurst Road
- Complete tar patching Arding Road
- Continue tar patching on rural roads
- Continue drainage in Uralla
- Continue renewing the causeway on Dog Trap Road
- Continue mowing and weed spraying in Uralla and Bundarra
- Continue cleaning kerb and gutters in Uralla