Council Works Report 16 December 2022

Civil Infrastructure Works for the week ending 16 December 2022

  • Continue Tolleys Gully Construction
  • Complete dig outs MR73 ready for stabilizing
  • Continue dig outs Barraba Road
  • Continue driveway laybacks Roman Street
  • Continue slashing rural and regional roads
  • Complete cleaning sediment dam at Uralla water treatment plant
  • Continue tar patching rural and regional roads
  • Continue mowing in Uralla and Bundarra

 

Planned works next week, commencing 19 December 2022

  • Continue Tolleys Gully Construction
  • Continue dig outs Barraba Road
  • Continue grading Barraba Road
  • Continue dig outs MR73
  • Continue tar patching rural and regional roads
  • Continue mowing in Uralla and Bundarra

 

 

 

 

 

 

 

 

 