Council Works Report 22 April 2022

Civil Infrastructure Works for the week ending 22 April 2022

  • Continued drainage on Hawthorne Drive Construction
  • Completed grading Gwydir Park Road
  • Completed grading Woodlands Road
  • Commenced grading Carlowrie Road
  • Ceased grading wash outs on Hillview Road ready for gravel resheeting
  • Continued tar patching on Regional Roads
  • Continued whipper snipping around guard rails on bridge approaches
  • Repaired damaged stormwater grate in Maitland Street
  • Continued drainage maintenance on Rural Roads
  • Continued mowing in Uralla and Bundarra
  • Completed clearing at Fuller Park ready for replanting trees
  • Continued heavy patches on Kingstown Road using contractor Stabilcorp (see photos)
  • Prepared Alma Park and started implementing Traffic Management Plan for Anzac Day

 

Works scheduled next week, commencing 26 April 2022

  • Continue drainage on Hawthorne Drive Construction
  • Complete grading Carlowrie Road
  • Commence grading Old Kingstown Road
  • Complete gravel re-sheeting on Munsies Road
  • Recommence grading washouts on Hillview Road ready for gravel re-sheeting
  • Continue tar patching on Regional Roads
  • Continue mowing in Uralla and Bundarra
  • Prepare sporting fields for local schools’ sports carnivals
  • Finalise heavy patches on Kingstown Road using contractor Stabilcorp
  • Commence heavy patching on Bundarra Road west from Barbados Corner by Stabilcorp

 

Rural-Road-Maintenence.jpg