Council Works Report 22 July 2022

Civil Infrastructure Works for the week ending 22 July 2022

  • Continue sub grade on Hawthorne Drive construction (see photo)
  • Commence grading Barraba Road
  • Commence grading Mihi Road
  • Complete winning gravel for gravel resheeting Bindawalla Road
  • Fix heavy patch west of Merilba on Kingstown Road for the moment until we get more workers back to fix it properly
  • Continue tar patching on rural roads (only running 1 tar truck at the moment)
  • Continue drainage on rural roads (see photo)
  • Continue cleaning up broken limbs in Uralla and Bundarra
  • Continue cleaning footpaths and gutters in Uralla and Bundarra

Works scheduled next week, commencing 25 July 2022

  • Complete sub grade to Phil Gunners - commence sub grade on final 200m to Northeys Road on Hawthorne Drive construction
  • Complete grading Barraba Road
  • Commence grading Bakers Creek Road
  • Complete grading Mihi Road
  • Commence grading Lindfield Road
  • Continue tar patching on rural roads
  • Continue drainage on rural roads
  • Continue cleaning  foot paths and kerb and gutters in Uralla and Bundarra

 

Rural-Road-Maintenence.jpg