Council Works Report 22 September 2023

Civil Infrastructure works undertaken week ending 22 September 2023:

  • Complete batter works Ferndale Hill rehab
  • Continue grading Balala Road
  • Complete grading Allinghams Road
  • Complete grading Dalveen Road
  • Continue grading Barraba Road
  • Clean drainage pipes in and around Bundarra
  • Tar patch edges Thunderbolts Way North
  • Tar patch Bindawalla Road
  • Continue culvert and footpath concreting for The Glen Project
  • Assist with water main and service replacement Warwick Street
  • Commence spraying footpaths, kerb and gutters
  • Continue maintenance footpaths, parks and cemeteries Uralla and Bundarra

 

Planned works for week commencing 25 September 2023

  • Bitumen seal Ferndale Hill Rehab, Monday (contractors)
  • Guidepost and spot mark Ferndale Hill
  • Commence Granite overlay Warwick St Rehab
  • Continue Grading Balala Road
  • Commence grading Lana Road
  • Continue tar patching edges Thunderbolts Way North
  • Commence tar patching edges Gwydir River Road
  • Continue footpath concreting The Glen Project
  • Commence spraying small lawns for bindii and broadleaf
  • Continue maintenance footpaths, parks and cemeteries Uralla and Bundarra

 

 