Council Works Report 27 August 2021

Civil Infrastructure Works for the week ending 27 August 2021

  • Wet conditions severely restricted progress on our construction and maintenance grading works
  • Continued grading Baldersleigh Road
  • Continued tar patching on regional roads
  • Continued street furniture refurbishment.
  • Continued sign maintenance in Uralla and on rural roads
  • Continued with Tolleys Gully Bridge abutments
  • Continued preparing and forming up Old Gostwyck, Corey & Hariet Gully Roads for sealing
  • Continued grading Glenburnie Road
  • Continued Bendemeer Street Bundarra footpath upgrade
  • Gravel patched water damage on Gostwyck, Mihi, Linfield and Hillview Road
  • Gravel patched water damage on Balala, Danehurst, and Primrose Hill Road

Works scheduled next week, commencing 30 August 2021

  • Continue tar patching on rural and regional roadsRural-Road-Maintenence.jpg
  • Continue drainage maintenance in Uralla and rural roads
  • Continue street furniture refurbishment
  • Continue multipurpose sports courts landscaping in Bundarra
  • Continue Tolleys Gully Bridge abutments
  • Continue Hawthorne Drive Construction Stage 1
  • Continue preparing and forming up Old Gostwyck, Corey & Hariet Gully Roads for sealing
  • Continue Bendemeer Street footpath upgrade
  • Continue grading Glenburnie Road
  • Commence grading Laura Homestead Road
  • Commence grading Waterworks Road
  • Commence grading Green Gully Road