Council Works Report 3 December 2021

Civil Infrastructure Works for the week ending 3 December 2021

  • Continued sub base on Tolleys Gully Bridge Construction
  • Completed earthworks and sub base and start base course on Bergen Road black spot (see photo)
  • Completed drainage on Mt Drummond Road
  • Commenced backfilling (landscaping) Multi-Purpose Courts in Bundarra
  • Continued drainage and repairson rural roads after floods
  • Continued tar patching on rural and regional roads
  • Completed slashing Arding, Invergowrie, MR124, MR73 Central, Kingstown, Torryburn, Gostwyck areas
  • Continued mowing and weed spraying in Uralla and Bundarra
  • Sealing to the northern section of Barleyfields Road (except at the the rail crossing) by UPC – scheduled for Friday)

Bergen-Road-Black-Spot.jpg

Works scheduled next week, commencing 6 December 2021

  • Continue sub base on Tolleys Gully Bridge Construction
  • Complete base course on Bergen Road black spot
  • Commence grading Gowans Road
  • Commence approach slabs on Tolleys Gully Bridge Construction
  • Continue tar patching on rural and regional roads
  • Continue slashing where needed
  • Complete backfilling Multi-Purpose Courts in Bundarra
  • Continue mowing and weed spraying in Uralla and Bundarra
  • Complete painting light poles at the crossing in Bridge Street
  • Commence weeding in Alma Park