Council Works Report 5 January 2024

Civil Infrastructure works undertaken week ending 5 January 2024:

  • Complete grading Dog Trap Road
  • Commence grading Everton Vale Road
  • Complete fence Bundarra School crossing
  • Install pipes Goodes Road
  • Clean out sediment dam Uralla Water Works
  • Continue slashing rural roads (Invergowrie)
  • Continue maintenance footpaths parks and cemeteries

 

Planned works for week commencing 8 January 2024

  • Recommence Kingstown Road rehabilitation
  • Continue grading Baldersleigh Road
  • Complete grading Everton Vale Road
  • Commence grading Williams Road
  • Continue works Industrial Area
  • Continue slashing regional and rural roads
  • Continue tar patching
  • Continue maintenance footpaths parks and cemeteries

 