Council Works Report 9 February 2023

Civil Infrastructure works undertaken week ending 9 February 2024:

  • Continue rehabilitation Tolleys – Scrubby Gully
  • Complete grading Primrose Hill Road
  • Commence grading Clerks Road
  • Continue tar patching regional and rural roads
  • Commence electrical testing and tagging
  • Continue pipe and drainage works various
  • Continue maintenance footpaths parks and cemeteries

 

Planned works for week commencing 12 February 2024 

  • Continue rehabilitation works Tolleys - Scrubby Gully
  • Commence grading Ferris Lane
  • Commence grading Panseyfields Road
  • Complete grading Clerks Road
  • Commence grading Georges Creek Road
  • Continue tar patching regional and rural roads
  • Continue slashing regional and rural roads
  • Continue pipe and drainage works various areas
  • Continue maintenance footpaths parks and cemeteries

 

 

 

 

 